Research on Deformation Patterns and Influencing Factors of Ten Pilot Tunnel Pile Method Construction in Large Span Metro Stations

[Objective] To ensure the construction safety of large span metro stations, it is necessary to conduct research on the deformation patterns of the station structure and the influencing factors in the construction process of ten pilot tunnel pile method. [Method] With Xihuang Village Station as the e...

Full description

Saved in:
Bibliographic Details
Main Author: ZHOU Tao
Format: Article
Language:zho
Published: Urban Mass Transit Magazine Press 2025-01-01
Series:Chengshi guidao jiaotong yanjiu
Subjects:
Online Access:https://umt1998.tongji.edu.cn/journal/paper/doi/10.16037/j.1007-869x.2025.01.010.html
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1841543653651120128
author ZHOU Tao
author_facet ZHOU Tao
author_sort ZHOU Tao
collection DOAJ
description [Objective] To ensure the construction safety of large span metro stations, it is necessary to conduct research on the deformation patterns of the station structure and the influencing factors in the construction process of ten pilot tunnel pile method. [Method] With Xihuang Village Station as the engineering background, a numerical model for the construction of ten pilot tunnel pile method in large span stations is established. The patterns of ground settlement law and the pile horizontal deformation patterns at different construction stages are analyzed. The influence pattern of the three factors, namely the excavation sequence of pilot tunnels, the staggered distance of pilot tunnel excavations, and the construction sequence of arch closing, on the ground settlement is studied. [Result & Conclusion] The construction of the upper pilot tunnels and the middle pilot tunnels above the station has a greater impact on the ground settlement. The ground settlement patterns of each construction stage all conform to the normal distribution. The maximum settlement locates at the center line of the station,and the ground settlement caused by the pilot tunnel construction and the arch closing construction accounts for 74.7% of the total settlement. After the excavation of the soil on the second basement level of the station, the horizontal restraint of the piles is sharply weakened, resulting in increased horizontal deformation of the piles. The ground settlement caused by the first excavation of the lower pilot tunnels is relatively small. As the staggered distance of the pilot tunnel excavation increases, the maximum ground settlement gradually decreases. The construction sequence of first excavating the side arch closings and then successively excavating the middle arch closings causes the least ground settlement.
format Article
id doaj-art-efd00abdd38744e189cbcd8b44a425d1
institution Kabale University
issn 1007-869X
language zho
publishDate 2025-01-01
publisher Urban Mass Transit Magazine Press
record_format Article
series Chengshi guidao jiaotong yanjiu
spelling doaj-art-efd00abdd38744e189cbcd8b44a425d12025-01-13T08:04:42ZzhoUrban Mass Transit Magazine PressChengshi guidao jiaotong yanjiu1007-869X2025-01-01281566010.16037/j.1007-869x.2025.01.010Research on Deformation Patterns and Influencing Factors of Ten Pilot Tunnel Pile Method Construction in Large Span Metro StationsZHOU Tao0Changsha Urban Investment Infrastructure Construction Project Management Co, Ltd, 410011 ,changsha, China[Objective] To ensure the construction safety of large span metro stations, it is necessary to conduct research on the deformation patterns of the station structure and the influencing factors in the construction process of ten pilot tunnel pile method. [Method] With Xihuang Village Station as the engineering background, a numerical model for the construction of ten pilot tunnel pile method in large span stations is established. The patterns of ground settlement law and the pile horizontal deformation patterns at different construction stages are analyzed. The influence pattern of the three factors, namely the excavation sequence of pilot tunnels, the staggered distance of pilot tunnel excavations, and the construction sequence of arch closing, on the ground settlement is studied. [Result & Conclusion] The construction of the upper pilot tunnels and the middle pilot tunnels above the station has a greater impact on the ground settlement. The ground settlement patterns of each construction stage all conform to the normal distribution. The maximum settlement locates at the center line of the station,and the ground settlement caused by the pilot tunnel construction and the arch closing construction accounts for 74.7% of the total settlement. After the excavation of the soil on the second basement level of the station, the horizontal restraint of the piles is sharply weakened, resulting in increased horizontal deformation of the piles. The ground settlement caused by the first excavation of the lower pilot tunnels is relatively small. As the staggered distance of the pilot tunnel excavation increases, the maximum ground settlement gradually decreases. The construction sequence of first excavating the side arch closings and then successively excavating the middle arch closings causes the least ground settlement.https://umt1998.tongji.edu.cn/journal/paper/doi/10.16037/j.1007-869x.2025.01.010.htmllarge span metro tunnelten pilot tunnels construction with pile-beam-arch methodconstruction deformation patterninfluencing factor
spellingShingle ZHOU Tao
Research on Deformation Patterns and Influencing Factors of Ten Pilot Tunnel Pile Method Construction in Large Span Metro Stations
Chengshi guidao jiaotong yanjiu
large span metro tunnel
ten pilot tunnels construction with pile-beam-arch method
construction deformation pattern
influencing factor
title Research on Deformation Patterns and Influencing Factors of Ten Pilot Tunnel Pile Method Construction in Large Span Metro Stations
title_full Research on Deformation Patterns and Influencing Factors of Ten Pilot Tunnel Pile Method Construction in Large Span Metro Stations
title_fullStr Research on Deformation Patterns and Influencing Factors of Ten Pilot Tunnel Pile Method Construction in Large Span Metro Stations
title_full_unstemmed Research on Deformation Patterns and Influencing Factors of Ten Pilot Tunnel Pile Method Construction in Large Span Metro Stations
title_short Research on Deformation Patterns and Influencing Factors of Ten Pilot Tunnel Pile Method Construction in Large Span Metro Stations
title_sort research on deformation patterns and influencing factors of ten pilot tunnel pile method construction in large span metro stations
topic large span metro tunnel
ten pilot tunnels construction with pile-beam-arch method
construction deformation pattern
influencing factor
url https://umt1998.tongji.edu.cn/journal/paper/doi/10.16037/j.1007-869x.2025.01.010.html
work_keys_str_mv AT zhoutao researchondeformationpatternsandinfluencingfactorsoftenpilottunnelpilemethodconstructioninlargespanmetrostations