Delay Analysis of Atlas Sports Club Project Based on FTA and ETA

The development of infrastructure and commercial facilities in Indonesia continues to increase along with urbanization and economic growth, but delays in construction projects are still a significant problem. The Atlas Sport Club project in Pantai Indah Kapuk 2 (PIK 2) experienced delays caused by v...

Full description

Saved in:
Bibliographic Details
Main Authors: Devita Sari, Hamonangan Girsang
Format: Article
Language:English
Published: University of Brawijaya 2025-06-01
Series:Rekayasa Sipil
Subjects:
Online Access:https://rekayasasipil.ub.ac.id/index.php/rs/article/view/1263/667
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1850215155485376512
author Devita Sari
Hamonangan Girsang
author_facet Devita Sari
Hamonangan Girsang
author_sort Devita Sari
collection DOAJ
description The development of infrastructure and commercial facilities in Indonesia continues to increase along with urbanization and economic growth, but delays in construction projects are still a significant problem. The Atlas Sport Club project in Pantai Indah Kapuk 2 (PIK 2) experienced delays caused by various factors, such as design changes, material delays, lack of communication, labor shortages, ineffective supervisory control, and extreme weather conditions. This research aims to identify and analyze the factors causing delays in the Atlas Sport Club project in PIK 2 and provide recommendations for mitigation strategies for similar projects in the future. Using quantitative and qualitative mixed methods, data was analyzed using validity and reliability tests and FTA (Fault Tree Analysis) and ETA (Event Tree Analysis) methods to understand the main causes and their impacts. The study found that work method error was the dominant factor with a probability of 0.8987. The five mitigations obtained from the pivotal event of the ETA method are completing the design and specifications at the beginning of the project; the financial process runs smoothly, the need for human resources that are by the needs and have good capabilities and experience; jointly reviewing work methods, initial designs at regular meetings; and finally procuring materials according to specifications.
format Article
id doaj-art-7bf97f8c2f1b49449136c53bd1ff9322
institution OA Journals
issn 1978-5658
2502-6348
language English
publishDate 2025-06-01
publisher University of Brawijaya
record_format Article
series Rekayasa Sipil
spelling doaj-art-7bf97f8c2f1b49449136c53bd1ff93222025-08-20T02:08:42ZengUniversity of BrawijayaRekayasa Sipil1978-56582502-63482025-06-0119219120210.21776/ub.rekayasasipil.2025.019.02.7Delay Analysis of Atlas Sports Club Project Based on FTA and ETADevita Sari0Hamonangan Girsang1Civil Engineering Department, Mercubuana University, 11650, IndonesiaEngineering Profession Department, Mercubuana University, 11650, IndonesiaThe development of infrastructure and commercial facilities in Indonesia continues to increase along with urbanization and economic growth, but delays in construction projects are still a significant problem. The Atlas Sport Club project in Pantai Indah Kapuk 2 (PIK 2) experienced delays caused by various factors, such as design changes, material delays, lack of communication, labor shortages, ineffective supervisory control, and extreme weather conditions. This research aims to identify and analyze the factors causing delays in the Atlas Sport Club project in PIK 2 and provide recommendations for mitigation strategies for similar projects in the future. Using quantitative and qualitative mixed methods, data was analyzed using validity and reliability tests and FTA (Fault Tree Analysis) and ETA (Event Tree Analysis) methods to understand the main causes and their impacts. The study found that work method error was the dominant factor with a probability of 0.8987. The five mitigations obtained from the pivotal event of the ETA method are completing the design and specifications at the beginning of the project; the financial process runs smoothly, the need for human resources that are by the needs and have good capabilities and experience; jointly reviewing work methods, initial designs at regular meetings; and finally procuring materials according to specifications.https://rekayasasipil.ub.ac.id/index.php/rs/article/view/1263/667delayetaftaspss
spellingShingle Devita Sari
Hamonangan Girsang
Delay Analysis of Atlas Sports Club Project Based on FTA and ETA
Rekayasa Sipil
delay
eta
fta
spss
title Delay Analysis of Atlas Sports Club Project Based on FTA and ETA
title_full Delay Analysis of Atlas Sports Club Project Based on FTA and ETA
title_fullStr Delay Analysis of Atlas Sports Club Project Based on FTA and ETA
title_full_unstemmed Delay Analysis of Atlas Sports Club Project Based on FTA and ETA
title_short Delay Analysis of Atlas Sports Club Project Based on FTA and ETA
title_sort delay analysis of atlas sports club project based on fta and eta
topic delay
eta
fta
spss
url https://rekayasasipil.ub.ac.id/index.php/rs/article/view/1263/667
work_keys_str_mv AT devitasari delayanalysisofatlassportsclubprojectbasedonftaandeta
AT hamonangangirsang delayanalysisofatlassportsclubprojectbasedonftaandeta