Delay Analysis of Atlas Sports Club Project Based on FTA and ETA
The development of infrastructure and commercial facilities in Indonesia continues to increase along with urbanization and economic growth, but delays in construction projects are still a significant problem. The Atlas Sport Club project in Pantai Indah Kapuk 2 (PIK 2) experienced delays caused by v...