Extended Ultimate-Pit-Limit Methodology for Optimizing Surface-to-Underground Mining Transition in Metal Mines

The transition from surface mining to underground is a critical issue for metal mines. The commonly cited procedure cored by ultimate-pit-limit (UPL) methodology is restricted to maximize the profit from both surface and underground mining, due to the absence of the integration of the profit from ei...

Full description

Saved in:
Bibliographic Details
Main Authors: Si-Tong Ren, Yang Liu, Xin-Yi Yang, Ding-Gui Tong, Gao-Feng Ren
Format: Article
Language:English
Published: Wiley 2022-01-01
Series:Advances in Civil Engineering
Online Access:http://dx.doi.org/10.1155/2022/2753991
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1849467776362610688
author Si-Tong Ren
Yang Liu
Xin-Yi Yang
Ding-Gui Tong
Gao-Feng Ren
author_facet Si-Tong Ren
Yang Liu
Xin-Yi Yang
Ding-Gui Tong
Gao-Feng Ren
author_sort Si-Tong Ren
collection DOAJ
description The transition from surface mining to underground is a critical issue for metal mines. The commonly cited procedure cored by ultimate-pit-limit (UPL) methodology is restricted to maximize the profit from both surface and underground mining, due to the absence of the integration of the profit from either of them. Under the target for such maximization, this study proposes a new optimization approach, which directly relates the design of open-pit limit and underground stopes, by equalizing the marginal profit from either surface or underground mining. The variation of the crown pillar size is involved in this approach. The proposed approach is applied to the Dagushan iron mine, and results show the total profit increased from 3.79 billion CNYs (original design by conventional UPL methodology) to 4.17 billion CNYs (optimal design by the proposed approach), by 9.91%. Moreover, the marginal profit from surface and underground mining, as well as total profit, of all possible designs of surface-to-underground mining transition in Dagushan iron mine is calculated to validate the proposed approach. When the marginal profits satisfy the criterion of the proposed approach, the maximum value of the total profit appears, and this demonstrates the proposed approach is robust to maximize the total profit in surface-to-underground mining transition. This work contributes to existing literature studies primarily from practical aspect, by providing a unified approach to optimize the transition from surface to underground mining.
format Article
id doaj-art-e63147751f4a432db3f866124c938d33
institution Kabale University
issn 1687-8094
language English
publishDate 2022-01-01
publisher Wiley
record_format Article
series Advances in Civil Engineering
spelling doaj-art-e63147751f4a432db3f866124c938d332025-08-20T03:26:04ZengWileyAdvances in Civil Engineering1687-80942022-01-01202210.1155/2022/2753991Extended Ultimate-Pit-Limit Methodology for Optimizing Surface-to-Underground Mining Transition in Metal MinesSi-Tong Ren0Yang Liu1Xin-Yi Yang2Ding-Gui Tong3Gao-Feng Ren4School of Resources and Civil EngineeringSchool of Resources and Environmental EngineeringDepartment of FinanceChina Resources Cement (Jinsha) LimitedSchool of Resources and Environmental EngineeringThe transition from surface mining to underground is a critical issue for metal mines. The commonly cited procedure cored by ultimate-pit-limit (UPL) methodology is restricted to maximize the profit from both surface and underground mining, due to the absence of the integration of the profit from either of them. Under the target for such maximization, this study proposes a new optimization approach, which directly relates the design of open-pit limit and underground stopes, by equalizing the marginal profit from either surface or underground mining. The variation of the crown pillar size is involved in this approach. The proposed approach is applied to the Dagushan iron mine, and results show the total profit increased from 3.79 billion CNYs (original design by conventional UPL methodology) to 4.17 billion CNYs (optimal design by the proposed approach), by 9.91%. Moreover, the marginal profit from surface and underground mining, as well as total profit, of all possible designs of surface-to-underground mining transition in Dagushan iron mine is calculated to validate the proposed approach. When the marginal profits satisfy the criterion of the proposed approach, the maximum value of the total profit appears, and this demonstrates the proposed approach is robust to maximize the total profit in surface-to-underground mining transition. This work contributes to existing literature studies primarily from practical aspect, by providing a unified approach to optimize the transition from surface to underground mining.http://dx.doi.org/10.1155/2022/2753991
spellingShingle Si-Tong Ren
Yang Liu
Xin-Yi Yang
Ding-Gui Tong
Gao-Feng Ren
Extended Ultimate-Pit-Limit Methodology for Optimizing Surface-to-Underground Mining Transition in Metal Mines
Advances in Civil Engineering
title Extended Ultimate-Pit-Limit Methodology for Optimizing Surface-to-Underground Mining Transition in Metal Mines
title_full Extended Ultimate-Pit-Limit Methodology for Optimizing Surface-to-Underground Mining Transition in Metal Mines
title_fullStr Extended Ultimate-Pit-Limit Methodology for Optimizing Surface-to-Underground Mining Transition in Metal Mines
title_full_unstemmed Extended Ultimate-Pit-Limit Methodology for Optimizing Surface-to-Underground Mining Transition in Metal Mines
title_short Extended Ultimate-Pit-Limit Methodology for Optimizing Surface-to-Underground Mining Transition in Metal Mines
title_sort extended ultimate pit limit methodology for optimizing surface to underground mining transition in metal mines
url http://dx.doi.org/10.1155/2022/2753991
work_keys_str_mv AT sitongren extendedultimatepitlimitmethodologyforoptimizingsurfacetoundergroundminingtransitioninmetalmines
AT yangliu extendedultimatepitlimitmethodologyforoptimizingsurfacetoundergroundminingtransitioninmetalmines
AT xinyiyang extendedultimatepitlimitmethodologyforoptimizingsurfacetoundergroundminingtransitioninmetalmines
AT dingguitong extendedultimatepitlimitmethodologyforoptimizingsurfacetoundergroundminingtransitioninmetalmines
AT gaofengren extendedultimatepitlimitmethodologyforoptimizingsurfacetoundergroundminingtransitioninmetalmines