Comprehensive Construction Method for Shield Receiving in Water-rich Silty Sand Stratum
[Objective]To address the issue of cutterhead damage and subsequent work stoppages caused by unidentified obstructions during the construction of Zhengzhou Metro Line 3 tunnel, it is essential to study comprehensive construction methods for shield receiving in water-rich silty sand stratum. [Method]...
Saved in:
| Main Authors: | CHEN Yubing, LIU Zhihe, XIAO Fangqi, LIU Wei, LIU Nianwu, GAN Xiaolu, CHEN Shenghan |
|---|---|
| Format: | Article |
| Language: | zho |
| Published: |
Urban Mass Transit Magazine Press
2024-12-01
|
| Series: | Chengshi guidao jiaotong yanjiu |
| Subjects: | |
| Online Access: | https://umt1998.tongji.edu.cn/journal/paper/doi/10.16037/j.1007-869x.2024.12.026.html |
| Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Similar Items
-
Unstuck Technology for EPB/TBM Dual Mode Shield Machine Stuck in Rock Stratum
by: DUAN Yueqiang
Published: (2025-01-01) -
Treatment Technology for Grout Eruption during Large Diameter Slurry Shield Tunneling Machine Crossing the Water-Rich Sand Layer at the River Bottom
by: SUN Mingxiang
Published: (2025-05-01) -
Metro Tunnel Shield Construction in Highly Water-rich Karst Strata
by: ZHAO Heming
Published: (2025-03-01) -
Stability Study of Shield Tunnel Excavation Face Induced by Shield Chamber Pressure Entering in Shallow-Buried Sand Stratum
by: GE Jun
Published: (2025-01-01) -
Machine learning-based forecasting of ground surface settlement induced by metro shield tunneling construction
by: Qiankun Wang, et al.
Published: (2024-12-01)