Application of Fuzzy theory to project scheduling with critical path method
In this paper, we analyze the project scheduling problem using fuzzy theory. The crisp activity durations are modeled as triangular fuzzy sets. Fuzzy forward pass was carried out to determine fuzzy activity earliest start, fuzzy event earliest time and fuzzy activity earliest finish times. In order...
Saved in:
Main Authors: | , |
---|---|
Format: | Article |
Language: | English |
Published: |
Joint Coordination Centre of the World Bank assisted National Agricultural Research Programme (NARP)
2013-07-01
|
Series: | Journal of Applied Sciences and Environmental Management |
Online Access: | https://www.Ajol.Info/index.php/jasem/article/view/90482 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
_version_ | 1823864683194482688 |
---|---|
author | MH Oladeinde DO Itsisor |
author_facet | MH Oladeinde DO Itsisor |
author_sort | MH Oladeinde |
collection | DOAJ |
description | In this paper, we analyze the project scheduling problem using fuzzy
theory. The crisp activity durations are modeled as triangular fuzzy sets. Fuzzy forward pass was carried out to determine fuzzy activity earliest start, fuzzy event earliest time and fuzzy activity earliest finish times. In order to overcome the occurrence of negative fuzzy numbers which occurs in fuzzy backward pass using fuzzy subtraction, we apply a modified fuzzy backward pass technique which uses a recursive relation to obtain the fuzzy event latest; fuzzy activity latest start and fuzzy activity latest finish times. Through
numerical examples, we determine the criticality of the project activities and hence the critical path(s). The results obtained using the present method is compared with those obtained using other methods used in literature |
format | Article |
id | doaj-art-59ade43813fc4ea8950628b81f73b9fd |
institution | Kabale University |
issn | 2659-1502 2659-1499 |
language | English |
publishDate | 2013-07-01 |
publisher | Joint Coordination Centre of the World Bank assisted National Agricultural Research Programme (NARP) |
record_format | Article |
series | Journal of Applied Sciences and Environmental Management |
spelling | doaj-art-59ade43813fc4ea8950628b81f73b9fd2025-02-08T19:52:11ZengJoint Coordination Centre of the World Bank assisted National Agricultural Research Programme (NARP)Journal of Applied Sciences and Environmental Management2659-15022659-14992013-07-01171Application of Fuzzy theory to project scheduling with critical path methodMH OladeindeDO ItsisorIn this paper, we analyze the project scheduling problem using fuzzy theory. The crisp activity durations are modeled as triangular fuzzy sets. Fuzzy forward pass was carried out to determine fuzzy activity earliest start, fuzzy event earliest time and fuzzy activity earliest finish times. In order to overcome the occurrence of negative fuzzy numbers which occurs in fuzzy backward pass using fuzzy subtraction, we apply a modified fuzzy backward pass technique which uses a recursive relation to obtain the fuzzy event latest; fuzzy activity latest start and fuzzy activity latest finish times. Through numerical examples, we determine the criticality of the project activities and hence the critical path(s). The results obtained using the present method is compared with those obtained using other methods used in literaturehttps://www.Ajol.Info/index.php/jasem/article/view/90482 |
spellingShingle | MH Oladeinde DO Itsisor Application of Fuzzy theory to project scheduling with critical path method Journal of Applied Sciences and Environmental Management |
title | Application of Fuzzy theory to project scheduling with critical path method |
title_full | Application of Fuzzy theory to project scheduling with critical path method |
title_fullStr | Application of Fuzzy theory to project scheduling with critical path method |
title_full_unstemmed | Application of Fuzzy theory to project scheduling with critical path method |
title_short | Application of Fuzzy theory to project scheduling with critical path method |
title_sort | application of fuzzy theory to project scheduling with critical path method |
url | https://www.Ajol.Info/index.php/jasem/article/view/90482 |
work_keys_str_mv | AT mholadeinde applicationoffuzzytheorytoprojectschedulingwithcriticalpathmethod AT doitsisor applicationoffuzzytheorytoprojectschedulingwithcriticalpathmethod |