Cause Analysis and Prevention of Hole Collapse by Water Injection and Dust Removal in Qi Panjing Coal Mine

To solve the “special coal seam” with complex coal seam structure, fault phenomenon, and many gangue layers and complex gangue lithology in Qi Panjing coal mine, the problems such as hole collapse and blockage of coal seam water injection dust removal drilling are caused. From the aspects of drillin...

Full description

Saved in:
Bibliographic Details
Main Authors: Hua Guo, Hai-Qiao Wang, Shi-Qiang Chen, Zhi-Rong Wu
Format: Article
Language:English
Published: Wiley 2020-01-01
Series:Geofluids
Online Access:http://dx.doi.org/10.1155/2020/8814015
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1849306753156513792
author Hua Guo
Hai-Qiao Wang
Shi-Qiang Chen
Zhi-Rong Wu
author_facet Hua Guo
Hai-Qiao Wang
Shi-Qiang Chen
Zhi-Rong Wu
author_sort Hua Guo
collection DOAJ
description To solve the “special coal seam” with complex coal seam structure, fault phenomenon, and many gangue layers and complex gangue lithology in Qi Panjing coal mine, the problems such as hole collapse and blockage of coal seam water injection dust removal drilling are caused. From the aspects of drilling layout, drilling technology, and gangue material consolidation, a complete set of key technologies for prevention and control of water injection and dust removal in “special coal seam,” have been formed. Seven boreholes have been drilled in I020902 return air roadway of Qi Panjing coal mine, and field comparative test has been carried out. The results show that: after adopting the complete set of key technologies of drilling prevention and control, the drilling depth is 85-100 m, the average depth is 98 m, and the drilling depth of coal seam water injection can reach 170-185 m; the footage per cycle is greatly improved, with the minimum increase of 30.86%, the maximum increase of 46.38%, and the average increase of 36.77%, to save drilling time and bring good economic benefits, and there is no collapse in the borehole hole, to ensure the safety of production. It has a good reference, and practical guiding significance for other coal mining faces, especially for “special coal seam” working face.
format Article
id doaj-art-23a663ddca2d4aeb9d19416c70a7639d
institution Kabale University
issn 1468-8115
1468-8123
language English
publishDate 2020-01-01
publisher Wiley
record_format Article
series Geofluids
spelling doaj-art-23a663ddca2d4aeb9d19416c70a7639d2025-08-20T03:54:58ZengWileyGeofluids1468-81151468-81232020-01-01202010.1155/2020/88140158814015Cause Analysis and Prevention of Hole Collapse by Water Injection and Dust Removal in Qi Panjing Coal MineHua Guo0Hai-Qiao Wang1Shi-Qiang Chen2Zhi-Rong Wu3School of Resource, Environment and Safety Engineering, Hunan University of Science and Technology, Xiangtan, 411201 Hunan, ChinaSchool of Resource, Environment and Safety Engineering, Hunan University of Science and Technology, Xiangtan, 411201 Hunan, ChinaHunan Provincial Engineering Techniques Research Centre of Mine Ventilation & Dedusting Equipment, Hunan University of Science and Technology, 411201 Hunan, ChinaSchool of Resource, Environment and Safety Engineering, Hunan University of Science and Technology, Xiangtan, 411201 Hunan, ChinaTo solve the “special coal seam” with complex coal seam structure, fault phenomenon, and many gangue layers and complex gangue lithology in Qi Panjing coal mine, the problems such as hole collapse and blockage of coal seam water injection dust removal drilling are caused. From the aspects of drilling layout, drilling technology, and gangue material consolidation, a complete set of key technologies for prevention and control of water injection and dust removal in “special coal seam,” have been formed. Seven boreholes have been drilled in I020902 return air roadway of Qi Panjing coal mine, and field comparative test has been carried out. The results show that: after adopting the complete set of key technologies of drilling prevention and control, the drilling depth is 85-100 m, the average depth is 98 m, and the drilling depth of coal seam water injection can reach 170-185 m; the footage per cycle is greatly improved, with the minimum increase of 30.86%, the maximum increase of 46.38%, and the average increase of 36.77%, to save drilling time and bring good economic benefits, and there is no collapse in the borehole hole, to ensure the safety of production. It has a good reference, and practical guiding significance for other coal mining faces, especially for “special coal seam” working face.http://dx.doi.org/10.1155/2020/8814015
spellingShingle Hua Guo
Hai-Qiao Wang
Shi-Qiang Chen
Zhi-Rong Wu
Cause Analysis and Prevention of Hole Collapse by Water Injection and Dust Removal in Qi Panjing Coal Mine
Geofluids
title Cause Analysis and Prevention of Hole Collapse by Water Injection and Dust Removal in Qi Panjing Coal Mine
title_full Cause Analysis and Prevention of Hole Collapse by Water Injection and Dust Removal in Qi Panjing Coal Mine
title_fullStr Cause Analysis and Prevention of Hole Collapse by Water Injection and Dust Removal in Qi Panjing Coal Mine
title_full_unstemmed Cause Analysis and Prevention of Hole Collapse by Water Injection and Dust Removal in Qi Panjing Coal Mine
title_short Cause Analysis and Prevention of Hole Collapse by Water Injection and Dust Removal in Qi Panjing Coal Mine
title_sort cause analysis and prevention of hole collapse by water injection and dust removal in qi panjing coal mine
url http://dx.doi.org/10.1155/2020/8814015
work_keys_str_mv AT huaguo causeanalysisandpreventionofholecollapsebywaterinjectionanddustremovalinqipanjingcoalmine
AT haiqiaowang causeanalysisandpreventionofholecollapsebywaterinjectionanddustremovalinqipanjingcoalmine
AT shiqiangchen causeanalysisandpreventionofholecollapsebywaterinjectionanddustremovalinqipanjingcoalmine
AT zhirongwu causeanalysisandpreventionofholecollapsebywaterinjectionanddustremovalinqipanjingcoalmine