Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project
In the implementation of construction projects, complex challenges are often faced, one of which is project delays. This research aims to analyze the application of the Fast Track Construction (FTC) method based on time variables in the delay of the SII Office Surabaya building construction project...
Saved in:
_version_ | 1823860887525523456 |
---|---|
author | Pasca Fitri Febriani Rizal Bahaswan Julistyana Tistogondo |
author_facet | Pasca Fitri Febriani Rizal Bahaswan Julistyana Tistogondo |
author_sort | Pasca Fitri Febriani |
collection | DOAJ |
description |
In the implementation of construction projects, complex challenges are often faced, one of which is project delays. This research aims to analyze the application of the Fast Track Construction (FTC) method based on time variables in the delay of the SII Office Surabaya building construction project. This research uses a quantitative method by collecting secondary data from the project contractor. The analysis was conducted on the remaining structural and architectural work using the Critical Path Method (CPM) and Microsoft Project. The research results show that of the three acceleration analyses with the FTC 50% method, 4 hours/day overtime and 6 hours/day overtime, the most effective and efficient application is with 4 hours/day overtime. With the addition of overtime, it is known that the more overtime is added, the less it reduces the duration of work items but can reduce the indirect costs of the project. And based on the results of statistical analysis using the Paired T Test, it was found that Ha was accepted and Ho was rejected, which means that the data is significant.
|
format | Article |
id | doaj-art-19bbf0bebdb3498492b244cc670868cb |
institution | Kabale University |
issn | 2597-4742 2597-4777 |
language | English |
publishDate | 2024-12-01 |
publisher | LPPM Narotama University |
record_format | Article |
series | The Spirit of Society Journal: International Journal of Society Development and Engagement |
spelling | doaj-art-19bbf0bebdb3498492b244cc670868cb2025-02-10T09:14:33ZengLPPM Narotama UniversityThe Spirit of Society Journal: International Journal of Society Development and Engagement2597-47422597-47772024-12-018110.29138/scj.v8i1.2941Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction ProjectPasca Fitri Febriani0Rizal Bahaswan1Julistyana Tistogondo2Universitas NarotamaUniversitas NarotamaUniversitas Narotama In the implementation of construction projects, complex challenges are often faced, one of which is project delays. This research aims to analyze the application of the Fast Track Construction (FTC) method based on time variables in the delay of the SII Office Surabaya building construction project. This research uses a quantitative method by collecting secondary data from the project contractor. The analysis was conducted on the remaining structural and architectural work using the Critical Path Method (CPM) and Microsoft Project. The research results show that of the three acceleration analyses with the FTC 50% method, 4 hours/day overtime and 6 hours/day overtime, the most effective and efficient application is with 4 hours/day overtime. With the addition of overtime, it is known that the more overtime is added, the less it reduces the duration of work items but can reduce the indirect costs of the project. And based on the results of statistical analysis using the Paired T Test, it was found that Ha was accepted and Ho was rejected, which means that the data is significant. https://jurnal.narotama.ac.id/index.php/link/article/view/1692%0Ahttps:/jurnal.narotama.ac.id/index.php/link/article/download/1692/1161/index.php/tsl/index.php/njts/index.php/maju/index.php/maju/index.php/ijebd/article/view/2612/index.php/jap/index.php/ijeeit/index.php/mgs/index.php/mgs/index.php/ijebd/index.php/scj/public/journals/10/journalThumbnail_en_US.jpg/index.php/index/public/journals/10/journalThumbnail_en_US.jpg/public/journals/26/journalThumbnail_en_US.jpg/public/journals/16/journalThumbnail_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/index.php/ijieeb/index.php/scj/article/view/2837/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/23/journalThumbnail_en_US.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/21/journalThumbnail_en_US.png/public/journals/19/journalThumbnail_en_US.jpg/public/journals/19/journalThumbnail_en_US.jpg/index.php/mgs/public/journals/20/journalThumbnail_en_US.jpg/index.php/jap/index.php/scj/article/view/2941fast trackvariable work overtimework delaysbuilding construction |
spellingShingle | Pasca Fitri Febriani Rizal Bahaswan Julistyana Tistogondo Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project The Spirit of Society Journal: International Journal of Society Development and Engagement fast track variable work overtime work delays building construction |
title | Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project |
title_full | Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project |
title_fullStr | Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project |
title_full_unstemmed | Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project |
title_short | Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project |
title_sort | implementation analysis of fast track and variable work overtime on delays in the building construction project |
topic | fast track variable work overtime work delays building construction |
url | https://jurnal.narotama.ac.id/index.php/link/article/view/1692%0Ahttps:/jurnal.narotama.ac.id/index.php/link/article/download/1692/1161/index.php/tsl/index.php/njts/index.php/maju/index.php/maju/index.php/ijebd/article/view/2612/index.php/jap/index.php/ijeeit/index.php/mgs/index.php/mgs/index.php/ijebd/index.php/scj/public/journals/10/journalThumbnail_en_US.jpg/index.php/index/public/journals/10/journalThumbnail_en_US.jpg/public/journals/26/journalThumbnail_en_US.jpg/public/journals/16/journalThumbnail_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/index.php/ijieeb/index.php/scj/article/view/2837/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/23/journalThumbnail_en_US.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/21/journalThumbnail_en_US.png/public/journals/19/journalThumbnail_en_US.jpg/public/journals/19/journalThumbnail_en_US.jpg/index.php/mgs/public/journals/20/journalThumbnail_en_US.jpg/index.php/jap/index.php/scj/article/view/2941 |
work_keys_str_mv | AT pascafitrifebriani implementationanalysisoffasttrackandvariableworkovertimeondelaysinthebuildingconstructionproject AT rizalbahaswan implementationanalysisoffasttrackandvariableworkovertimeondelaysinthebuildingconstructionproject AT julistyanatistogondo implementationanalysisoffasttrackandvariableworkovertimeondelaysinthebuildingconstructionproject |