Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project

In the implementation of construction projects, complex challenges are often faced, one of which is project delays. This research aims to analyze the application of the Fast Track Construction (FTC) method based on time variables in the delay of the SII Office Surabaya building construction project...

Full description

Saved in:
Bibliographic Details
Main Authors: Pasca Fitri Febriani, Rizal Bahaswan, Julistyana Tistogondo
Format: Article
Language:English
Published: LPPM Narotama University 2024-12-01
Series:The Spirit of Society Journal: International Journal of Society Development and Engagement
Subjects:
Online Access:https://jurnal.narotama.ac.id/index.php/link/article/view/1692%0Ahttps:/jurnal.narotama.ac.id/index.php/link/article/download/1692/1161/index.php/tsl/index.php/njts/index.php/maju/index.php/maju/index.php/ijebd/article/view/2612/index.php/jap/index.php/ijeeit/index.php/mgs/index.php/mgs/index.php/ijebd/index.php/scj/public/journals/10/journalThumbnail_en_US.jpg/index.php/index/public/journals/10/journalThumbnail_en_US.jpg/public/journals/26/journalThumbnail_en_US.jpg/public/journals/16/journalThumbnail_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/index.php/ijieeb/index.php/scj/article/view/2837/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/23/journalThumbnail_en_US.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/21/journalThumbnail_en_US.png/public/journals/19/journalThumbnail_en_US.jpg/public/journals/19/journalThumbnail_en_US.jpg/index.php/mgs/public/journals/20/journalThumbnail_en_US.jpg/index.php/jap/index.php/scj/article/view/2941
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1823860887525523456
author Pasca Fitri Febriani
Rizal Bahaswan
Julistyana Tistogondo
author_facet Pasca Fitri Febriani
Rizal Bahaswan
Julistyana Tistogondo
author_sort Pasca Fitri Febriani
collection DOAJ
description In the implementation of construction projects, complex challenges are often faced, one of which is project delays. This research aims to analyze the application of the Fast Track Construction (FTC) method based on time variables in the delay of the SII Office Surabaya building construction project. This research uses a quantitative method by collecting secondary data from the project contractor. The analysis was conducted on the remaining structural and architectural work using the Critical Path Method (CPM) and Microsoft Project. The research results show that of the three acceleration analyses with the FTC 50% method, 4 hours/day overtime and 6 hours/day overtime, the most effective and efficient application is with 4 hours/day overtime. With the addition of overtime, it is known that the more overtime is added, the less it reduces the duration of work items but can reduce the indirect costs of the project. And based on the results of statistical analysis using the Paired T Test, it was found that Ha was accepted and Ho was rejected, which means that the data is significant.
format Article
id doaj-art-19bbf0bebdb3498492b244cc670868cb
institution Kabale University
issn 2597-4742
2597-4777
language English
publishDate 2024-12-01
publisher LPPM Narotama University
record_format Article
series The Spirit of Society Journal: International Journal of Society Development and Engagement
spelling doaj-art-19bbf0bebdb3498492b244cc670868cb2025-02-10T09:14:33ZengLPPM Narotama UniversityThe Spirit of Society Journal: International Journal of Society Development and Engagement2597-47422597-47772024-12-018110.29138/scj.v8i1.2941Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction ProjectPasca Fitri Febriani0Rizal Bahaswan1Julistyana Tistogondo2Universitas NarotamaUniversitas NarotamaUniversitas Narotama In the implementation of construction projects, complex challenges are often faced, one of which is project delays. This research aims to analyze the application of the Fast Track Construction (FTC) method based on time variables in the delay of the SII Office Surabaya building construction project. This research uses a quantitative method by collecting secondary data from the project contractor. The analysis was conducted on the remaining structural and architectural work using the Critical Path Method (CPM) and Microsoft Project. The research results show that of the three acceleration analyses with the FTC 50% method, 4 hours/day overtime and 6 hours/day overtime, the most effective and efficient application is with 4 hours/day overtime. With the addition of overtime, it is known that the more overtime is added, the less it reduces the duration of work items but can reduce the indirect costs of the project. And based on the results of statistical analysis using the Paired T Test, it was found that Ha was accepted and Ho was rejected, which means that the data is significant. https://jurnal.narotama.ac.id/index.php/link/article/view/1692%0Ahttps:/jurnal.narotama.ac.id/index.php/link/article/download/1692/1161/index.php/tsl/index.php/njts/index.php/maju/index.php/maju/index.php/ijebd/article/view/2612/index.php/jap/index.php/ijeeit/index.php/mgs/index.php/mgs/index.php/ijebd/index.php/scj/public/journals/10/journalThumbnail_en_US.jpg/index.php/index/public/journals/10/journalThumbnail_en_US.jpg/public/journals/26/journalThumbnail_en_US.jpg/public/journals/16/journalThumbnail_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/index.php/ijieeb/index.php/scj/article/view/2837/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/23/journalThumbnail_en_US.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/21/journalThumbnail_en_US.png/public/journals/19/journalThumbnail_en_US.jpg/public/journals/19/journalThumbnail_en_US.jpg/index.php/mgs/public/journals/20/journalThumbnail_en_US.jpg/index.php/jap/index.php/scj/article/view/2941fast trackvariable work overtimework delaysbuilding construction
spellingShingle Pasca Fitri Febriani
Rizal Bahaswan
Julistyana Tistogondo
Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project
The Spirit of Society Journal: International Journal of Society Development and Engagement
fast track
variable work overtime
work delays
building construction
title Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project
title_full Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project
title_fullStr Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project
title_full_unstemmed Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project
title_short Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project
title_sort implementation analysis of fast track and variable work overtime on delays in the building construction project
topic fast track
variable work overtime
work delays
building construction
url https://jurnal.narotama.ac.id/index.php/link/article/view/1692%0Ahttps:/jurnal.narotama.ac.id/index.php/link/article/download/1692/1161/index.php/tsl/index.php/njts/index.php/maju/index.php/maju/index.php/ijebd/article/view/2612/index.php/jap/index.php/ijeeit/index.php/mgs/index.php/mgs/index.php/ijebd/index.php/scj/public/journals/10/journalThumbnail_en_US.jpg/index.php/index/public/journals/10/journalThumbnail_en_US.jpg/public/journals/26/journalThumbnail_en_US.jpg/public/journals/16/journalThumbnail_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/index.php/ijieeb/index.php/scj/article/view/2837/public/site/pageHeaderTitleImage_en_US.jpg/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/23/journalThumbnail_en_US.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/templates/images/ojs_brand.png/public/journals/21/journalThumbnail_en_US.png/public/journals/19/journalThumbnail_en_US.jpg/public/journals/19/journalThumbnail_en_US.jpg/index.php/mgs/public/journals/20/journalThumbnail_en_US.jpg/index.php/jap/index.php/scj/article/view/2941
work_keys_str_mv AT pascafitrifebriani implementationanalysisoffasttrackandvariableworkovertimeondelaysinthebuildingconstructionproject
AT rizalbahaswan implementationanalysisoffasttrackandvariableworkovertimeondelaysinthebuildingconstructionproject
AT julistyanatistogondo implementationanalysisoffasttrackandvariableworkovertimeondelaysinthebuildingconstructionproject