SCHEDULING ANALYSIS BEDUGUL VILLA CONSTRUCTION PROJECT USING PERT AND CPM METHODS

Scheduling in construction projects is necessary so that the planned time to complete the project can be achieved on time. the methods used in optimizing project scheduling are the Project Evaluation Review Technique (PERT) method and the Critical Path Method (CPM) method. Bedugul  Villa is one of t...

Full description

Saved in:
Bibliographic Details
Main Authors: Kiswara Agung Santoso, Ade Ratna Yusnita, Agustina Pradjaningsih
Format: Article
Language:English
Published: Universitas Pattimura 2024-03-01
Series:Barekeng
Subjects:
Online Access:https://ojs3.unpatti.ac.id/index.php/barekeng/article/view/9900
Tags: Add Tag
No Tags, Be the first to tag this record!
Description
Summary:Scheduling in construction projects is necessary so that the planned time to complete the project can be achieved on time. the methods used in optimizing project scheduling are the Project Evaluation Review Technique (PERT) method and the Critical Path Method (CPM) method. Bedugul  Villa is one of the projects that has been carried out with a work contract for 175 calendar days and the scheduling of which will be optimized in this study. The optimal duration for scheduling with the PERT method is to produce an optimal duration of 170 calendar days. The duration is 5 days faster than the existing schedule prepared by the project construction contractor, which is 175 calendar days. The probability of completion of the project is 87.7%. Calculations using the CPM method are 168 calendar days or 7 days earlier than the existing schedule made by the contractor.